Linx Residences Kallangur
Current Status:
Stage 1 – Building construction now complete
• Building construction is now complete
• Titles have been issued
• Settlements to commence
Stage 2 – Building construction now underway
• All slabs now down
• Frames have started on all blocks
• Cabinetry install now underway
• Garage doors install commencing
Monthly Look Ahead:
Stage 2
• Roofing to be completed
• Internal painters to commence
• Plumbing fit offs to commence
;
Nudgee Square Stage 2
Current Status:
Civil construction now completed, building construction underway
• 50% of slabs now poured
• Plumbers finishing last under slabs
• Carpenters have started on first frames
Monthly Look Ahead:
• Slab pours to continue
• First roof to be installed
• Plumbing and electrical rough ins to commence
Boondall Chase II
Current Status:
Civil construction has now commenced
• Site establishment complete
• Earthworks completed
• Stormwater drainage commenced
• Retaining walls underway
• Roadworks progressing
Monthly Look Ahead:
Civils to be well underway
• Stormwater drainage completion
• Retaining walls completion
• Building foundations to commence
• Underground power underway
• Plumbing and drainage underway